Proposed Water Main Renewal – Road Works

Four workers in safety gear repairing a water pipe in a trench on a rural road

Yorkshire Water are planning to replace the clean water mains on Arthington Lane (A659) in Pool in Wharfedale.

This section of water main has experienced a historically high number of repairs. By renewing it, we’re aiming to reduce the frequency of bursts and unplanned interruptions to supply, as well as improve overall water quality for customers in the area.

This is the closure breakdown; the other works will be completed under traffic lights and will extend to just past Tower Drive on Arthington Lane (A659).

DescriptionDuration (Weeks)Start DateFinish Date
Close Arthington Lane From the White Hart Public House to the Beeches, maintain access for residents  and Public house. 321/07/202609/08/2026
Close Arthington Lane From the Oakdale Drive to Stonedale Close, maintain access for residents . 310/08/202628/08/2026
Open Arthington Lane for Bank Holiday weekend3 Days28/08/202601/09/2026

YW are currently proposing to start work on 21 July 2026, with a full road closure implemented in two phases through to 28 August 2026. They will plan to open the road over the August bank holiday weekend. Following this, traffic management would move to temporary traffic signals, which are expected to remain in place until 5 December 2026.